Model 3 Production Hell: The Ramp That Nearly Broke Tesla

How Tesla went from 260 Model 3s in a quarter to 5,031 in a week: Elon Musk asleep at the factory, batteries built by hand and an assembly line in a tent.

6 min read 7 chapters Updated Explore the sources ↗
The first Model 3 cars lined up at their July 2017 delivery event
July 28, 2017: the first Model 3 delivery event. Thirty cars made the promise tangible; the next challenge was building them by the thousands. Photo: Steve Jurvetson / CC BY 2.0 · Resized and converted to WebP.
In this story 7 chapters

Lines before the reveal

On the morning of March 31, 2016, people lined up outside Tesla stores to put down money on a car none of them had seen. At some stores more than a hundred people were waiting before the doors opened. The Model 3 wouldn't be unveiled until that evening, at Tesla's design studio in Hawthorne, California, but reservations opened that day, in stores and online, with a refundable $1,000 deposit.

A red Model 3 prototype and a grey Model X on a lit stage above a crowd holding up phones.
The red Model 3 prototype on stage beside a Model X at the unveiling in Hawthorne, California, on the evening of March 31, 2016. Photo: Steve Jurvetson / CC BY 2.0 · Resized to 1600px on the long edge and converted to WebP; 1 area(s) Gaussian-blurred (radius 14) for privacy; nothing else altered.

Tesla had never handled anything like it. More than 180,000 reservations came in within 24 hours. Within a week the company said it held about 325,000, more than three times the number of Model S sedans it had sold through the end of 2015. Tesla had promised first deliveries in 2017, and every one of those deposits was a customer waiting for a car from a production line that didn't exist yet.

Sources for Lines before the reveal

Thirty cars and a warning

The first deliveries came on schedule, at least on paper. On the evening of July 28, 2017, Tesla held a handover party at the Fremont factory and gave the first 30 production Model 3s to their owners. By Elon Musk's count Tesla had built 50 cars by then, and the other 20 were kept for testing. Musk drove onto the stage in a red Model 3 and gave buyers the numbers they'd been waiting for: a Standard Range car starting at $35,000 in the US with 220 miles of range, and a Long Range version at $44,000 rated for 310 miles.

Rows of new red, white and black Tesla Model 3 sedans parked at Supercharger posts beside an event stage at dusk.
Some of the first production Model 3 cars wait at Superchargers before the July 28, 2017, handover event at the Fremont factory. Photo: Steve Jurvetson / CC BY 2.0 · Resized to 1600px on the long edge and converted to WebP; 4 area(s) Gaussian-blurred (radius 14) for privacy; nothing else altered.

Then he told the room what came next. Tesla, Musk said, faced at least six months of what he called manufacturing hell. The plan was steep all the same: about 100 cars in August, 1,500 in September and 20,000 in December.

Sources for Thirty cars and a warning

260 cars in a quarter

The plan broke almost immediately. When Tesla reported its third-quarter numbers in October 2017, it had built 260 Model 3s in the entire quarter, against a plan of 1,500 in September alone. Tesla blamed production bottlenecks. Musk called it production hell and put Tesla somewhere around the eighth circle.

Model 3 quarterly production: Q3 2017, 260; Q4 2017, 2,425; Q1 2018, 9,766; Q2 2018, 28,578 vehicles. Bars share a zero baseline.
The Model 3 ramp measured by whole quarters. Tesla's global production totals are not deliveries or extrapolated weekly rates; no market or trim split is supplied. View full diagram ↗ Original diagram: TeslaCarFacts. Sources: Tesla Q3 2017 release (Oct 2, 2017) Tesla Q4 2017 release (Jan 3, 2018) Tesla Q1 2018 release (Apr 3, 2018) Tesla Q2 2018 release (Jul 2, 2018)

The worst bottleneck wasn't in Fremont at all. It was at Gigafactory 1 in Nevada, on the line that packed battery cells into modules. Tesla said the module design and its automated assembly process had, between them, taken longer to get running than expected, and Panasonic's chief executive confirmed the battery bottleneck. In January 2018, Tesla employees told CNBC that parts of the pack process still weren't automated and that batteries had been built partly by hand as recently as mid-December, with workers borrowed from suppliers to help.

Tesla's Nevada Gigafactory in the desert east of Reno
Gigafactory Nevada, photographed in April 2021. Tesla's plan for more cars depended on making enough battery cells with Panasonic. Photo: Ken Lund / CC BY-SA 2.0 · Resized and converted to WebP.
Sources for 260 cars in a quarter

Too many robots, and a couch at the factory

In the spring of 2018 Musk said in public that he'd got it wrong. By the beginning of April he had taken direct control of Model 3 production. On April 13, replying on Twitter to a Wall Street Journal reporter, he wrote that excessive automation at Tesla was a mistake, his own mistake, and added the line that became the headline of the week: humans are underrated. In interviews he described a complicated network of conveyor belts at Fremont that hadn't worked. Tesla tore it out.

He was also, by his own description, living at the plant. In an April 2018 interview at Fremont, he showed Gayle King of CBS This Morning the conference-room couch where he slept when the work was intense, and said that on one recent night he'd slept on the floor because the couch was too narrow. King checked with employees, who confirmed it. After the segment aired, a YouTube creator started a GoFundMe to buy Musk a new couch. It raised more than $18,000, which went to charity.

A white Model S body on a red assembly cart inside the Fremont factory
Fremont's Model S line, photographed before the Model 3 ramp. The same factory would later face a much larger production challenge. Photo: Maurizio Pesce / CC BY 2.0 · Resized and converted to WebP; existing source edits retained.
Sources for Too many robots, and a couch at the factory

An assembly line under a tent

Tearing out robots wasn't enough to reach the target of 5,000 Model 3s a week. Tesla needed another general assembly line, and it had no building to put one in. So it put up a tent. At Fremont, crews erected a Sprung structure, a kind of engineered tent sturdy enough to be used permanently, and filled it with a new line built largely from spare parts. Tesla dates the first Model 3 off that line to June 8, 2018, and on June 16 Musk announced on Twitter that the company had built an entire new general assembly line in about three weeks.

The new line was called GA4. It ran mostly on people instead of robots while engineers kept working on the automated lines indoors. In its July 2, 2018 release, Tesla said GA3, its regular Model 3 line, was expected to reach 5,000 a week on its own soon, and that GA4 had got the company there sooner. The tent built roughly 20 percent of the Model 3s Tesla produced in the final seven days of June.

In the final seven days of June 2018, Tesla produced 5,031 Model 3s. GA4 accounted for roughly 20 percent; roughly 80 percent is remaining Model 3 output. The 1,913 Model S/X cars produced that week are outside this Model 3 denominator.
Tesla reported the figures on July 2 for the final seven days of June. The roughly 20% share does not supply an exact GA4 unit count; the remainder does not identify a detailed assembly-line split. One reported week is not a sustained production rate. View full diagram ↗ Original diagram: TeslaCarFacts. Sources: Tesla Q2 2018 release, July 2: final-week Model 3 output and GA4 share
Sources for An assembly line under a tent

5,031 Model 3s in seven days

The deadline Tesla had set for itself was the end of the second quarter. In the last seven days of June 2018, Fremont built 5,031 Model 3s along with 1,913 Model S and Model X vehicles. Tesla's total output for the quarter was 53,339 vehicles, 55 percent more than in the first quarter and the most in its history to that point.

Q2 2018 Model 3: 28,578 produced and 18,440 delivered globally. Two bars use the same zero-to-30,000-vehicle scale.
Two different measures in the same quarter: completed cars and customer deliveries. Subtracting one from the other does not give quarter-end inventory or the number in transit. Tesla's release did not split these totals by trim or market. View full diagram ↗ Original diagram: TeslaCarFacts. Sources: Tesla Q2 2018 release (Jul 2, 2018)

One good week wasn't a steady rate yet. Tesla said it repeated a week of roughly 5,000 Model 3s several times in July, and set its next goal at 6,000 a week by late August. The plan from July 2017 had called for 20,000 cars in December, roughly 5,000 a week. Tesla got there about six months late, and at first only one week at a time.

Sources for 5,031 Model 3s in seven days

What the ramp left behind

The payoff showed up the next quarter. For the third quarter of 2018, Tesla reported GAAP net income of $312 million on revenue of $6.82 billion. The Model 3 was the best-selling car in the United States by revenue that quarter and fifth by unit volume, and Tesla said its gross margin on the car was above 20 percent. Cash on hand rose by $731 million, with $881 million of free cash flow.

The costs were real too. In 2019, workers who had staffed the GA4 tent described to CNBC the pressure they'd been under to hit Model 3 production goals. By December 2018, Forbes was already framing the next test: Tesla had survived manufacturing hell, and keeping production steady and profitable was the harder part.

The tent, put up as a stopgap, never came down. It was still assembling Model 3s a year after the crisis, and it later took on the Model Y. In October 2024 Tesla posted two dates under the words "Big tent came a long way": June 8, 2018, the first Model 3 out of GA4, and October 25, 2024, the 1 millionth Model Y built there.

The Model 3 ramp is usually told as the story of one executive asleep on a factory floor. A lot more people were in it: battery engineers nursing a module line that wouldn't run, supplier workers building packs by hand, crews putting up a building and a production line in three weeks, and assembly workers in a tent turning out one Model 3 in five during the final seven days of June 2018.

A red Tesla Model 3
A red Model 3. Photo: Steve Jurvetson (derivative: Mariordo) / CC BY 2.0 · Resized and converted to WebP; existing source edits retained.
Sources for What the ramp left behind

The cars in this story

Sources

  1. Electrek: Tesla Model 3, in-store reservations a success as impressive lines form
  2. Electrek: Tesla has now over 325,000 Model 3 reservations, timeline of events
  3. Green Car Reports: Tesla Model 3 Unveil On March 31, Deposits Accepted That Day
  4. Wikipedia: Tesla Model 3
  5. Electrek: Tesla sends out Model 3 Delivery Event invites to select few owners
  6. Teslarati: Tesla Model 3 'handover party' will be on July 28, first 30 customers will receive keys
  7. Green Car Reports: 2017 Tesla Model 3 prices, features, details from handover party
  8. Forbes: As Tesla Delivers First Model 3s, Musk Warns Of 'Manufacturing Hell' Ahead
  9. NBC News: It will be 'hell' to ramp up production of Tesla Model 3, says Musk
  10. CNBC: Tesla Model 3 deliveries lower than expected because of 'production bottlenecks'
  11. Electrek: Tesla Model 3, Elon Musk hints at 'production hell' at battery Gigafactory
  12. Electrek: Tesla Model 3 bottleneck confirmed to be at Gigafactory 1, Panasonic CEO
  13. CNBC: Tesla employees say to expect more Model 3 delays, citing Gigafactory problems
  14. TechCrunch: Elon Musk says 'humans are underrated,' calls Tesla's 'excessive automation' a mistake
  15. Elon Musk on X: reply to Tim Higgins on excessive automation
  16. CBS News: Elon Musk, Tesla CEO talks Model 3; he's 'stressed,' but 'optimistic'
  17. CNBC: Elon Musk is stressed, says he's sleeping on Tesla factory floor to save time
  18. CNBC: A YouTube star raised money to buy Elon Musk a couch and gave it to charity
  19. Electrek: Tesla's new Model 3 assembly line inside a 'tent' is 'way better'
  20. Quartz: Watch Tesla build a giant tent for its new Model 3 assembly line in three weeks
  21. Tesla on X: Big tent came a long way, June 8, 2018, first Model 3 from GA4
  22. Teslarati: Elon Musk explains why Tesla built a tent for its new Model 3 assembly line
  23. CleanTechnica: In The Last 7 Days Of Q2, Tesla Produced 5031 Model 3
  24. Tesla, Inc. Form 10-Q for the quarter ended June 30, 2018 (SEC)
  25. Tesla, Inc. Form 8-K, Q3 2018 update letter (SEC)
  26. Electrive: Tesla releases Q3 earnings, record revenue and a profit
  27. CNBC: Tesla workers in GA4 tent describe pressure to make Model 3 goals
  28. Forbes: Tesla Survived Manufacturing Hell, Now Comes The Hard Part
  29. Interesting Engineering: Elon Musk Hands Over New Tesla Model 3 Cars to First 30 Buyers
  30. Tesla Q2 2018 production and deliveries, July 2, 2018
  31. Drive Tesla Canada: Tesla's Fremont factory builds its 1 millionth Model Y

More stories

Spot an error or a change we missed? Suggest a correction.